Ezyquip was engaged by Rolleston Coal to provide mining infrastructure support for the C2418 Early Works package for the Rolleston West Infrastructure Project. The project required a reliable wet hire partner capable of delivering modified plant, experienced operators, and responsive project support within strict timeframes.
Drawing on our extensive experience delivering mining infrastructure support and supporting civil projects across regional and remote Australia, Ezyquip provided a tailored solution that combined high-performance equipment with skilled operators to help prepare critical infrastructure for future site expansion.
Hire Type
Location
Equipment Type
Equipment Supplied
To support the earthworks and site preparation activities, Ezyquip deployed:
• 4 x CAT 637K Scrapers
• CAT 14M Grader
• 2 x CAT D8T Dozers
• Service Truck
• Water Truck
• Fitters
This fleet enabled efficient bulk earthworks, grading, site preparation, and ongoing maintenance support throughout the project.
The Challenge
The project presented several operational challenges, including tight deadlines for plant modifications, the mobilisation of qualified operators, and maintaining continuity across a remote worksite.
In addition, daily billing accuracy and resource planning required close coordination between Ezyquip and the client to ensure transparency and effective project delivery.
The Ezyquip Solution
Ezyquip worked closely with the Rolleston Coal project team throughout the project, conducting regular site visits and weekly stakeholder meetings to maintain strong communication and alignment. By developing trusted relationships on site and remaining responsive to changing requirements, we were able to proactively resolve issues, support project objectives, and ensure works progressed without impacting critical schedules.
Our team:
• Delivered all required plant modifications within the allocated timeframes.
• Coordinated operator mobilisation, including travel and site inductions.
• Implemented daily billing communication and weekly reconciliation meetings.
• Leveraged resources from multiple branch locations to maintain workforce continuity.
• Maintained open communication channels to quickly respond to changing site requirements.
Results:
Through proactive project management and responsive customer support, Ezyquip successfully:
• Delivered all modified equipment on schedule.
• Maintained consistent operator coverage throughout the project.
• Established a transparent and reliable billing process.
• Responded rapidly to changing project requirements.
• Strengthened our partnership with Rolleston Coal through dependable service and communication.
Why Ezyquip?
Projects like Rolleston West Infrastructure demonstrate Ezyquip’s ability to rapidly mobilise equipment and personnel while maintaining the flexibility required by large-scale mining infrastructure support and civil projects.
Our combination of quality equipment, experienced operators, and customer-focused project support enables clients to meet demanding schedules with confidence.
Whether supporting mining operations, civil construction, infrastructure development, renewable energy projects, pipelines, or remote works, Ezyquip delivers practical solutions that keep projects moving.